US 1 / State Road 5 Resurfacing Project Weekly Update 12/20/12
Downtown Biz, Downtown Boca, Uncategorized | Editor | Comments OffFollowing our weekly progress meeting, we offer this update for The US-1/ State Road 5 Resurfacing Project. December 20th, 2012 marks day 108 of 219 contract days. We currently have two approved weather days and two approved holiday days that were added to the contract time.
Please note that no work will take place between 12/24/2012 and 1/1/2013 due to holidays.